Practical completion of the processing plant is expected ahead of schedule in December.
13 December 2022
A 6m diameter return airway shaft has also broken through to surface.
15 November 2022
The decline is 250m vertically below the surface and 13m vertically below the top of the orebody.
17 October 2022
All key construction equipment from overseas suppliers is in country.
16 September 2022
Construction at Abra is 78% complete, with Galena starting installation of ball-mill components.
17 August 2022
Abra concentrate is to be exported from Geraldton port, as part of two recent contracts.
06 October 2021
Byrnecut has ordered equipment from Sandvik including an underground jumbo to use at Abra.
09 September 2021
Buzzing Perth roundtable picks the brains of sector leaders to help shape the resources
From flight schedules to emergency alerts, new screen-based platform Swift TV is helping mining companies better reach workers
THE BEST GET BETTER: the new Nexsys system
Boosting pipeline lifespan, cutting energy use, and lowering emissions in modern
The ESG Index provides an in-depth evaluation of the ESG performance of 60+ of the world’s largest mining companies. It assesses companies across 10 weighted indicators within 6 essential ESG pillars.
Discover how mining companies and investors are adopting, deploying and evaluating new technologies.
Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.
Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions