Gold expected in May at Dalgaranga

GASCOYNE Resources’ Dalgaranga gold project is about one month ahead of schedule and running under budget, with the process plant is 98% complete and on schedule for ore commissioning and first gold in May.

Gold expected in May at Dalgaranga Gold expected in May at Dalgaranga Gold expected in May at Dalgaranga Gold expected in May at Dalgaranga Gold expected in May at Dalgaranga

Construction of the cyclone tower at Dalgaranga nearing completion.

Dry commissioning is already underway.

Installation of the semi-autogenous grinding mill is nearing completion, as is the crusher and run-of-mine bin installations.