THE problematic ball mill at the Gold Road Resources-Gold Fields joint venture Gruyere gold mine, along with the rest of the comminution circuit, has operated successfully for 96 hours straight.

Gruyere mill racks up the hours Gruyere mill racks up the hours Gruyere mill racks up the hours Gruyere mill racks up the hours Gruyere mill racks up the hours

Gruyere's mills have managed 96 hours of continuous operation.

This is one of the main practical completion criteria for engineering, procurement and construction contractor the Amec Foster Wheeler-Civmec joint venture.