L-Max passes first test

LEPIDICO has confirmed the viability of its L-Max process through a 10-day continuous pilot plant campaign, with assay results supporting phase 1 plant design parameters.

L-Max passes first test L-Max passes first test L-Max passes first test L-Max passes first test L-Max passes first test

Lepidico's pilot plant

The pilot plant campaign resulted in an average lithium extraction rate of 94% to lithium sulphate, which is expected to rise further after some tweaks to the process, and a lithium loss rate of just