Beacon building at Jaurdi

ROUND the clock production of the Jaurdi processing plant is expected to occur this week as Beacon Minerals continues commissioning the 500,000 tonne per annum gold processing facility.

After running dayshift only for the past few weeks, Jaurdi is getting ready for round the clock operations.

After running dayshift only for the past few weeks, Jaurdi is getting ready for round the clock operations.

The plant, 35km northwest of Coolgardie, Western Australia, has been operating on day shift only for the past three weeks. Mill throughputs have been running 20% above the nominal nameplate capacity...

Start a free trial to continue reading this article
Already have an account?  
Subscribe now
MORE ON THIS TOPIC

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions

editions

Mining Magazine Intelligence Exploration Report 2023 (feat. Opaxe data)

A comprehensive review of current exploration rates, trending exploration technologies, a ranking of top drill intercepts and a catalogue of 2022 Initial Resource Estimates and recent discovery successes.