Heron on track for fourth quarter commissioning

WITH its final major operating contracts in place, Heron Resources is confident it is on track to start commissioning its Woodlawn zinc-copper operating in the fourth quarter both on time and within budget.

Heron on track for fourth quarter commissioning Heron on track for fourth quarter commissioning Heron on track for fourth quarter commissioning Heron on track for fourth quarter commissioning Heron on track for fourth quarter commissioning

First floor structural steel work in place on the flotation building.

All major earthworks on site have been completed with only minor items to be finalised.

Engineering design and procurement are 93% complete.