WAVE International has started working on the definitive feasibility study for the Gabanintha vanadium project run by Technology Metals Australia.

Making waves at Gabanintha Making waves at Gabanintha Making waves at Gabanintha Making waves at Gabanintha Making waves at Gabanintha

A schematic of Technology Metals' Gabanintha project

The start of the DFS follows delivery of the pre-feasibility study in late June.

The PFS was based on the 26 million tonnes of vanadium pentoxide, graded at 0.9%, in the Northern Block tenements, with the study confirming Gabanintha could be a high value, relatively low risk and technically strong development opportunity for Technology Metals.

The DFS will further develop the processing flowsheet, update plant engineering and site and infrastructure assessments and sort out major long lead time item tenders.

Other work involved in the DFS includes revising the open pit mine design to incorporate updated geotechnical data and scheduling, progression of environmental and heritage studies and provision of revised capital and operating cost estimates to a DFS leve...