Gruyere on target for June quarter first gold

CONSTRUCTION of the Gruyere process plant is 97% complete, the power station and high voltage sub-stations across the site are fully commissioned and mining has scaled up to double shifts.

So far 4.9 million bank cubic metres have been mine from the Gruyere open pit.

So far 4.9 million bank cubic metres have been mine from the Gruyere open pit.

Finishing works on the processing plant at the remote gold mine in Western Australia's Goldfields region are underway with commissioning handovers progressing. The primary crushing system was ore commissioned...

Start a free trial to continue reading this article
Already have an account?  
Subscribe now

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions

editions

Mining Magazine Intelligence Exploration Report 2023 (feat. Opaxe data)

A comprehensive review of current exploration rates, trending exploration technologies, a ranking of top drill intercepts and a catalogue of 2022 Initial Resource Estimates and recent discovery successes.