THE Beyondie sulphate of potash project in Western Australia’s eastern Pilbara is 63% complete with all planned brine production bores at 10 Mile and Sunshine fully commissioned and in operation.

Beyondie build gathers steam Beyondie build gathers steam Beyondie build gathers steam Beyondie build gathers steam Beyondie build gathers steam

SOP purification plant and power station construction.

According to Kalium Lakes' quarterly activity report construction was in full swing in September with 180 workers on site.