STRIKE Resources’ Paulsens East iron ore project will ramp up to full production of 2 million tonnes per annum in two stages, at a cost of $6.4 million.

Paulsens East test pit at eastern end of outcropping hematite ridge with detrital in foreground.

Paulsens East test pit at eastern end of outcropping hematite ridge with detrital in foreground.

According to an updated feasibility study on Paulsens East, in Western Australia's Pilbara, stage 1 production will target surface detrital and low strip ratio materials of up to 400,000t, which will be...

Start a free trial to continue reading this article
Already have an account?  
Subscribe now

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions

editions

Mining Magazine Intelligence Exploration Report 2023 (feat. Opaxe data)

A comprehensive review of current exploration rates, trending exploration technologies, a ranking of top drill intercepts and a catalogue of 2022 Initial Resource Estimates and recent discovery successes.