Abracadabra, 83%

THE Abra lead-silver mine Galena Mining is building in Western Australia’s Gascoyne region has reached 83% and, with the arrival of the flotation cells and regrind mills, all key construction equipment from overseas suppliers is in country.

Abracadabra, 83% Abracadabra, 83% Abracadabra, 83% Abracadabra, 83% Abracadabra, 83%

The crushing section conveyor being aligned at Galena Mining's Abra lead-silver project.

Galena managing director Tony James said with construction activities passing 83% completion, focus at the plant was shifting to installation of the remaining mechanical items, piping and electrical