Qld floods to drag down BHP's year

BHP Billiton is bracing for lower sales and production of coking coal plus higher unit costs at i...

Lou Caruana

This article is 14 years old. Images might not display.

The drop in production was mitigated by stockpiling and increased production from the company’s Illawarra Coal in New South Wales, with sales declining by 15% in the December quarter.

“The decision to increase pumping and drainage capacity following severe wet weather in the March 2008 quarter has minimised inpit water accumulation, although heavy rainfall that persisted for much of the December 2010 half-year has significantly restricted overburden removal,” BHP said.

“When combined with disruption to external infrastructure, we expect an ongoing impact on production, sales and unit costs for the remainder of the 2011 financial year.”

BHP’s total metallurgical coal production for the December quarter came in at 7.78 million tonnes.

The company continues to assess the impact of the extreme weather events and has confirmed that force majeure has been declared for the majority of its Bowen Basin operations, including Goonyella Riverside, Peak Downs, Norwich Park, Gregory Crinum, South Walker and Blackwater.

While Illawarra Coal recorded another quarter of “robust production” of 1.8Mt, the company warned that two longwall moves were expected to constrain volumes in the March 2011 quarter.

Total production for energy coal for the December quarter was 16.5Mt.

Quarterly production records were achieved at Hunter Valley Energy Coal for both the quarter and half-year, reflecting first production from the MAC20 project.

In late September last year, BHP finally received NSW government approval for its $784 million MAC20 project to extract up to 36Mt per annum of raw coal.

The MAC20 project involves an open cut expansion to the Mt Arthur mine, which will lift saleable thermal coal production by 3.5Mtpa.

Record exports from Hunter Valley Energy Coal for the quarter and half-year, which included a greater proportion of high ash sales, also reflected the ongoing ramp-up of the Newcastle Coal Infrastructure Group port facilities.

The increase in sales is occurring as operations experience adverse movements in currency markets, particularly in South Africa and Australia, and additional operating costs ahead of full production from the delivery of growth projects, BHP said.

Elsewhere, record rainfall continued to constrain production at Cerrejon Coal in Colombia. Production in the Americas was lower than the September quarter, largely due to an unplanned outage at New Mexico Coal (USA).

TOPICS:

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

ESG Index 2025: Benchmarking the Future of Sustainable Mining

The ESG Index provides an in-depth evaluation of the ESG performance of 60+ of the world’s largest mining companies. It assesses companies across 10 weighted indicators within 6 essential ESG pillars.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions