COAL of Africa has produced its first run-of-mine thermal coal from its key wholly owned Mooiplaa...

Blair Price

This article is 16 years old. Images might not display.

Revealed in its 2008 December quarter activities statement, the junior has now received and put into operation its second continuous miner and said the washing plant should be ready by March in time for production from the advanced stage underground mining portals.

First coal sales are expected in this year’s second quarter and over 150m of incline conveyor belt structure has been installed at this stage.

The previously announced negotiations with Transnet Freight Rail for moving coal to the Richards Bay terminal have been finalised, securing the Mooiplaats operation’s needs in a five-year agreement.

CoA said the freight company would satisfy the initial 900,000 tonne per annum port allocation and could supply more wagons to cater for 3 million tonnes per annum should the port terminal expansion plans proceed.

On the sales front, CoA said it had submitted an initial letter of offer to South African power utility Eskom with follow-on discussions expected to be concluded when export sales start from the mine in this year’s second quarter.

Other discussions are continuing with various parties over long-term export agreements in the meantime.

For its 74%-owned Vele coking coal project in Limpopo, CoA has lodged an environmental scoping report with South Africa’s Department of Minerals and Energy while specialist studies for the environmental management plan and impact assessment documents are to be sent through within the next couple of months.

Core sample analysis from three bulk drill sites is underway while the company said 12 holes were due for completion in early 2009 as part of its drilling program to define the site of the proposed bulk sample box cut.

A revised mine production schedule now includes both underground and open cut sections and is expected to improve coking coal yields, reduce mining costs and extend mine life to beyond 2040.

The New Order Mining Right application was submitted to the DME back in October and CoA said Vele was ready to start mining in the second half of this year providing it is granted.

Exploration at the company’s wholly owned Makhado project covered 3400m in the last three months of 2008 with the 20-hole large diameter drilling program having 12 holes completed by year-end.

Full results are expected in the second half of this year with CoA saying core analysis undertaken has yielded good quality hard coking coal.

Environmental documentation is underway while the NOMR application for the project is almost complete.

CoA aims to start up the project a year after Vele kicks off.

Meanwhile, CoA’s wholly owned Holfontein project sale to Lachland Star has been shelved as the latter company failed to receive shareholder approval.

As part of national legislative requirements, CoA said it had extended its Black Economic Empowerment agreement to the end of April 2009.

CoA managing director Simon Farrell said he was pleased with the progress made and said the company’s zero-debt and cash position made it well placed to bring the Mooiplaats, Vele and Makhado projects into production within the next two years despite the challenging global economic conditions.

TOPICS:

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions

editions

Automation and Digitalisation Insights 2024

Exclusive research for Mining IQ Automation and Digitalisation Insights 2024 shows mining companies are embracing cutting-edge tech