Eagle Downs mine completion delayed

UNCERTAINTY over the coal markets has led the Aquila Resources and Vale joint venture to reconfig...

Lou Caruana

This article is 12 years old. Images might not display.

The project – which involves construction, development and operation of an underground longwall hard coking coal mine over an estimated mine life of 47 years for all target seams – now has a budget of $97.2 million, Aquila executive chairman Tony Poli said.

“In light of continuing softness in the coal price environment, the participants requested Eagle Downs Coal Management Pty Ltd focus on critical path development tasks and reprioritise some of the scheduled early works,” Poli said.

“In response to this request, the manager has presented the participants with a work program and budget for FY2014 of $97.2 million, which has now been approved by the participants.

“The manager has advised the participants that the overall construction schedule will be slightly impacted, with its previously anticipated completion date of November 2016 now being revised to H1 CY2017.”

Aquila announced earlier this week that Eagle Downs would be cutting back on staff in response to the downturn in coal prices.

But the drop in the Australian dollar is making the project look more attractive, according to Poli.

“Aquila notes that short-term deferral of non-critical path expenditure has the potential to considerably improve the economics of the project, if contracts can be executed in a lower cost environment,” he said.

“Aquila also considers that the recent overdue correction of the Australian dollar, to realign with reduced commodity prices, is likely to provide an additional positive boost to the economics of the project.”

Eagle Downs Coal Management re-tendered the contracts at the mine in March because of the tougher operating environment in the industry.

Construction on site started with the establishment of site access via a 6km sealed all-weather road, construction of mine offices, site civil works, construction of the Powerlink substation for provision of site power and establishment of the initial gas drainage system, according to the company.

The excavation of the box cut for the construction of the portal access to the mine drifts started in February.

TOPICS:

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

ESG Index 2025: Benchmarking the Future of Sustainable Mining

The ESG Index provides an in-depth evaluation of the ESG performance of 60+ of the world’s largest mining companies. It assesses companies across 10 weighted indicators within 6 essential ESG pillars.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions