Maules Creek beats schedule

WHITEHAVEN Coal is two months ahead of schedule as it expects to rail the first coal of its $A767...

Blair Price

This article is 11 years old. Images might not display.

A strong performance by the construction team and contractors was credited for this outcome.

“That the result is an outstanding achievement by everyone involved in the construction of the Maules Creek mine and that the team should be commended,” Whitehaven managing director and CEO Paul Flynn said.

The first sales from the Gunnedah Basin project will be of a bypass thermal coal that is expected to exceed Newcastle benchmark specifications.

Whitehaven said the commissioning of the coal handling and preparation plant plus associated infrastructure would continue through to July 2015.

The miner is not expecting any issues to arise from a New South Wales government approved revision to the project’s biodiversity management plan (BMP).

“Under this revised BMP, clearing activities will be carried out in the period between 15 February and 30 April of each year,” Whitehaven said.

“This timing for clearance activities will have no impact on railing first coal in January 2015, nor will it impact any other key project milestones.”

The open cut project is targeting a rate of 6 million tonnes per annum of coal production over the first 12 months and has approval to ramp up to 13Mtpa run of mine.

At full capacity the mine is expected to employ 450 people and it is also aiming to ensure that 10% of this workforce is of indigenous descent within five years.

The decision made by the NSW Department of Planning to deny Whitehaven Coal a special permit to clear for the Maules Creek coal mine during the sensitive spring and early summer months has vindicated community concerns of its environmental impact, environmental group Lock the Gate said.

National coordinator for Lock the Gate Phil Laird said the stop work was a small victory in the long running battle.

“This now means that Whitehaven cannot clear any more forest at Maules Creek until mid February 2015,” he said.

TOPICS:

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

ESG Index 2025: Benchmarking the Future of Sustainable Mining

The ESG Index provides an in-depth evaluation of the ESG performance of 60+ of the world’s largest mining companies. It assesses companies across 10 weighted indicators within 6 essential ESG pillars.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions