INTERNATIONAL COAL NEWS

Whitehaven's Maules Creek mounts equipment-buying spree

WHITEHAVEN Coal has completed the financing and procurement arrangements for the mining fleet req...

Lou Caruana

This article is 11 years old. Images might not display.

Maules Creek - the largest coal mine under construction in Australia - is forecast to be complete in CY2015, with first coal expected to be railed in March 2015.

The equipment consists of 300t and 170t trucks, excavators and other ancillary equipment. The transaction completes the acquisition of all of the equipment required for the first stage of mining at Maules Creek without using any balance sheet capacity.

The mine, with an expected life-of-mine strip ratio of 6.4:1 and average life-of-mine FOB costs of $67/t, will be one of the lowest-cost open cut coal mines in Australia.

Its initial production rate is planned to be 6Mtpa, however, over a period of three years, production is expected to ramp to 13.0Mtpa ROM coal as additional equipment is sourced for the mine and markets are developed for the coal.

The water supply project which provides water for both the construction activity and permanently for the mine was completed in March. The work, performed by a local contractor Stripes Engineering, was the first significant and critical component of the project to be completed.

Rainfall in late March filled site dams and enabled compaction work to continue unimpeded on the various construction sites.

An additional benefit of the rainfall event is that water draw for the construction project from the Namoi River will be significantly reduced for several months, according to Whitehaven.

Another step for the project was completion of the second stage of the salvage works under the Aboriginal Archaeology and Cultural Heritage Management Plan.

The area covered by the salvage works includes both the box cut for the mine and the first three years planned mining area.

“The successful completion of this work in a relatively short time period reflects positively upon the strength of the working relationships held with the broader indigenous group engaged with Whitehaven on the project,” the company said.

“Rail line construction which represents the longest lead time item for the project remains on schedule.”

Downer was awarded the CHPP erection contract during the March quarter.

Downer has mobilized to the holding yards where the components of the CHPP have been stored near Narrabri.

Initial assembly has started, with major components to be transferred to the site shortly, Whitehaven said.

In another development, the Commonwealth Department of the Environment has concluded its review of the reports prepared by the independent ecologist on the biodiversity offset land package for the Maules Creek project.

TOPICS:

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

ESG Index 2025: Benchmarking the Future of Sustainable Mining

The ESG Index provides an in-depth evaluation of the ESG performance of 60+ of the world’s largest mining companies. It assesses companies across 10 weighted indicators within 6 essential ESG pillars.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions