Sedgman posts profit

BUCKING the trend somewhat, the company that made its name as a coal handling and preparation pla...

Noel Dyson

This article is 10 years old. Images might not display.

Sedgman’s result was boosted by higher combined sales revenue and improved margins in its Projects business.

Those benefits were partly offset by weaker revenues and margins in its Operations business.

The company cut its overheads and support costs by 32% from the corresponding period. A continued focus on cost control across the business is being maintained.

The company’s order book has grown to $596 million of contracted work in the Projects and Operations businesses as at December 31, compared with $385 million at June 30.

Combined sales revenue for the Projects business grew 24.5% to $104.7 million as engineering, procurement and construction projects at Boggabri, Aurora and Solomon progressed. In the prior corresponding period Mungari was the only major EPC project under construction.

The Projects’ underlying earnings before interest, tax and amortisation for HY2015 was $3.2 million.

The EBITA margin of 3% for the half-year was more than the -17.7% margin achieved in the same period last year.

Project margins increased due to making better use of project staff, lowering business costs and the recovery of previously impaired debtors.

Sedgman managing director Peter Watson said the company had performed well despite the challenging market.

“We have delivered cost reductions through a business restructure, refocused the organisation on our core global minerals strategy, strengthened our low-cost sourcing capability in China, refreshed our vision and successfully differentiated ourselves in a very competitive market,” he said.

Sedgman continued to win EPC projects across a range of commodities:

  • a $133 million EPC contract for GEMCO at its manganese mine in the Northern Territory;
  • a $59.8 million contract for the filtration plant at Alcoa’s Kwinana alumina refinery in Western Australia;
  • a $36.7 million contract for the turn-key delivery of the train load-out for Cockatoo Coal’s Baralaba mine in Queensland; and
  • the Thiess Sedgman Projects joint venture won a $64 million EPC contract for a modular iron ore processing plant at Fortescue Metals Group’s Solomon mine in WA.

However, that last project is being reviewed by FMG.

Combined sales revenue for the Operations business fell $20.3% to $55.6 million.

This was due to three operating sites Sedgman had managed in HY2014 on behalf of clients either closing down or being taken back over by their owners.

EBITA margin for Operations of 8.4% was within expectations as the business was still focusing on cost control.

Watson said with subdued market conditions continuing, opportunities were typically smaller scale with heightened expectation on delivery assurance and facility performance.

TOPICS:

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions

editions

Automation and Digitalisation Insights 2024

Exclusive research for Mining IQ Automation and Digitalisation Insights 2024 shows mining companies are embracing cutting-edge tech