UNIVERSAL Coal has secured $55 million in funding for its second open cut coal mining operation i...

Lou Caruana

Located in the Witbank coalfields, 100km northeast of Johannesburg, the first phase of the NCC project is scheduled to be fully commissioned later this year.

At full capacity, this will produce 2 million tonnes of coal per annum for high-end domestic markets. A long-term Coal Sales Agreement is being negotiated with both power and metallurgical off-takers for the use of NCC coal.

With reserves of 40.5 million tonnes, the mine is expected to have a life well of more than 20 years.

The financing facility will also be used to refinance the debt component of Universal Coal’s Kangala Colliery.

Universal Coal CEO Tony Weber said that since that mine had reached steady state operations, existing project finance facilities were being replaced with more favourable and flexible corporate debt facilities.

“We are entering an exciting growth phase,” he said.

“Once we reach steady state production at NCC, the company’s net production will have doubled. Further, by securing corporate debt financing on more favourable terms than project financing, Universal Coal’s net value will be significantly enhanced, and its ability to bring long-life, multi-product coal operations to full production demonstrated.”

Weber said ministerial approvals for NCC were expected early during the next quarter pending certain rectifications required by the Department of Mineral Resources.

Universal Coal has completed a bankable feasibility study for the initial phase of the NCC project, which has been approved by the board subject to finalisation of the CSA.

Project development will continue as scheduled, with on-site mining activities to start once the CSA is concluded.

The opencast tender process for mining at Roodekop has been completed and a preferred contractor nominated.

Contractual agreements are being drafted.

Tender documents for the construction of processing plants have been released to pre-selected parties, with adjudication and selection processes underway.

TOPICS:

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions

editions

Automation and Digitalisation Insights 2024

Exclusive research for Mining IQ Automation and Digitalisation Insights 2024 shows mining companies are embracing cutting-edge tech