A PRE‐FEASIBILITY study confirms an open pit mine and 500,000 tonne per annum carbon‐ in‐pulp gold treatment plant on the Jaurdi project in Western Australia’s Goldfields region will reap 126,000 ounces of recovered gold for proponent Beacon Minerals, and cost $21.4 million.

Jaurdi gold shines bright Jaurdi gold shines bright Jaurdi gold shines bright Jaurdi gold shines bright Jaurdi gold shines bright

Water bore testing at the Jaurdi project

According to the PFS undertaken by Kalgoorlie-based company Minecomp, the pre-production capital cost of $21.4 million will be paid back in just 11 months.