TAWANA Resources and Alliance Mineral Assets have started commissioning the dense media separation circuit at the Bald Hill lithium and tantalum mine in Western Australia’s Eastern Goldfields.

Bald Hill begins commissioning Bald Hill begins commissioning Bald Hill begins commissioning Bald Hill begins commissioning Bald Hill begins commissioning

The Bald Hill lithium and tantalum plant is starting commissioning.

The power plant is operational and the motor control centre and low voltage switch room has been commissioned.

Dry commissioning has begun and is planned to continue through February.