TAWANA Resources and Alliance Mineral Assets have started commissioning the dense media separation circuit at the Bald Hill lithium and tantalum mine in Western Australia’s Eastern Goldfields.

Noel Dyson
The Bald Hill lithium and tantalum plant is starting commissioning.

The Bald Hill lithium and tantalum plant is starting commissioning.

The power plant is operational and the motor control centre and low voltage switch room has been commissioned. Dry commissioning has begun and is planned to continue through February. Crushing and...

Start a free trial to continue reading this article
Already have an account?  
Subscribe now

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions

editions

Mining Magazine Intelligence Exploration Report 2023 (feat. Opaxe data)

A comprehensive review of current exploration rates, trending exploration technologies, a ranking of top drill intercepts and a catalogue of 2022 Initial Resource Estimates and recent discovery successes.