PROGRESSIVE commissioning has started on the crushing, grinding-gravity and leach circuits at the Eastern Goldfields-operated Davyhurst mill near Kalgoorlie.

Crushing on track at Davyhurst Crushing on track at Davyhurst Crushing on track at Davyhurst Crushing on track at Davyhurst Crushing on track at Davyhurst

The refurbished Davyhurst mill.

With refurbishment work successfully completed on the 1.2 million tonne per annum mill and the crushing circuit commissioned and operational attention turns to the grinding-gravity circuit.