GUJARAT NRE Coking Coal’s strategic plan for continuous operations at its New South Wales NRE No 1 Colliery and its staged growth of production is progressing well, with the longwall expected to be operating by December 2011.

Lou Caruana
Longwall at NRE No 1 on track for December 2011

In its annual report, the company said two applications were being prepared concurrently as required by the NSW Environment Planning and Assessment Act.

The first is for the continuation of operations of up to 1 million tonnes per annum and the second is for the expansion of operations up to 3Mtpa.

“Both submissions will also assess the implementation of major infrastructure to accommodate the company’s expansion proposals,” the company said.

“These proposals are expected to be submitted and approval gained during the coming period.

“The long-term focus is to utilise the modern engineering standards and best practice, to provide the most efficient ways of performing mining operations that maximises the proposed production levels, while also minimising potential adverse environmental impacts.”

Joy won the $A90 million contract to supply longwall equipment for the NRE No1 colliery in April.

Under the same contract, Gujarat said Joy will also supply a new 183m longwall coal clearance system in late 2013 to upgrade the equipment at Gujarat’s nearby Wongawilli mine.

The longwall is scheduled for commissioning by late 2011 and will initially cut coal from a 145m face before it widens up to 390m in the next five years.

The longer-term future of Gujarat’s NRE Wongawilli mine – which is also in the Illawarra region – has been allowed for by the joining of the Avondale and Wongawilli lease areas.

This ultimately provides access to resources located west and south of the current mining areas.

An application is being prepared for the continuation of operations up to 2Mtpa. The proposal is expected to be submitted and approval gained during the next financial year.

To increase production levels up to 3Mtpa, additional approval from the NSW Environment Planning and Assessment Act will also be required.

TOPICS:

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions

editions

Mining Magazine Intelligence Exploration Report 2023 (feat. Opaxe data)

A comprehensive review of current exploration rates, trending exploration technologies, a ranking of top drill intercepts and a catalogue of 2022 Initial Resource Estimates and recent discovery successes.