Narrabri production falls as longwall moves through known fault

WHITEHAVEN Coal’s Narrabri mine in New South Wales saw production in the September quarter plunge 36% below the June quarter as the longwall moved through known faulted section of the panel.

 The next longwall move from panel 109 to 110 is scheduled for the end of the third quarter of FY21.

The next longwall move from panel 109 to 110 is scheduled for the end of the third quarter of FY21.

For the September quarter, Narrabri achieved 1.6 million tonnes of managed run-of-mine production, which was also 8% below the previous corresponding period. "Production decreased in the quarter as...

Start a free trial to continue reading this article
Already have an account?  
Subscribe now

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence Future Fleets Report 2024

The report paints a picture of the equipment landscape and includes detailed profiles of mines that are employing these fleets

editions

Mining Magazine Intelligence Digitalisation Report 2023

An in-depth review of operations that use digitalisation technology to drive improvements across all areas of mining production

editions

Mining Magazine Intelligence Automation Report 2023

An in-depth review of operations using autonomous solutions in every region and sector, including analysis of the factors driving investment decisions

editions

Mining Magazine Intelligence Exploration Report 2023 (feat. Opaxe data)

A comprehensive review of current exploration rates, trending exploration technologies, a ranking of top drill intercepts and a catalogue of 2022 Initial Resource Estimates and recent discovery successes.