Gruyere mill racks up the hours

Gruyere mill racks up the hours

Processed 73,590t at an average recovery of 94.8% and average grade of 1.17 grams per tonne gold.

Design / Build

15 AUGUST 2019
Gruyere ready to ramp

Gruyere ready to ramp

Ball mill operation clears way for ramp-up.

Design / Build

05 AUGUST 2019
Gruyere gold pour

Gruyere gold pour

Ball mill problems still holding up commissioning.

Comminution

01 JULY 2019
Hole appears in Gruyere's timetable

Hole appears in Gruyere's timetable

Full process plant commissioning pushed back more than a month.

Design / Build

20 JUNE 2019
Gruyere on target for June quarter first gold

Gruyere on target for June quarter first gold

Process plant 97% complete.

Development

17 APRIL 2019
Another hole in Gruyere's costings

Another hole in Gruyere's costings

Gruyere cost blown out to $621 million.

Development

31 JULY 2018