Activity at Kat Gap

The Gekko gold processing plant was moved onto its cured foundations earlier this week

This article is 2 years old. Images might not display.

The 6500 tonnes of ore recovered from the pit was loaded onto two trucks and transported to the run-of-mine pad outside the processing facility.

The Gekko gold processing plant was moved onto its cured foundations earlier this week.

The heaviest parts of the plant, including the spinner, were placed on the pad and secured to the foundations.

 

Archived article: image not displayed.

First ore being offloaded at ROM pad at Kat Gap processing facility

 

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

A growing series of reports, each focused on a key discussion point for the mining sector, brought to you by the Mining Monthly Intelligence team.

editions

Mining Magazine Intelligence: Future Fleets Report 2025

MMI Future Fleets Report 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions

editions

Mining Magazine Intelligence: Automation and Digitalisation Report 2024

Exclusive research for Mining Magazine Intelligence Automation and Digitalisation Report 2024 shows mining companies are embracing cutting-edge tech

editions

ESG Mining Company Index: Benchmarking the Future of Sustainable Mining

The ESG Mining Company Index report provides an in-depth evaluation of ESG performance of 61 of the world's largest mining companies. Using a robust framework, it assesses each company across 9 meticulously weighted indicators within 6 essential pillars.

editions

Mining Magazine Intelligence Exploration Report 2024 (feat. Opaxe data)

A comprehensive review of exploration trends and technologies, highlighting the best intercepts and discoveries and the latest initial resource estimates.