INTERNATIONAL COAL NEWS

Drayton cutbacks

ANGLO American has blamed New South Wales government planning delays for its decision to cut back...

Blair Price

This article is 11 years old. Images might not display.

The announcement comes despite the NSW Minerals Council’s social media-harnessing campaign to voice support for the Drayton South extension project.

Concerns about the project’s chances skyrocketed after the Mining & Petroleum Gateway Panel determined it would significantly impact two Hunter Valley horse studs and a winery on December 10.

“We are persevering to secure state government approval for Drayton South but as a result of the delays with the approvals process we have run out of time to achieve the overlap we needed to keep the entire workforce employed while we developed the project,” Drayton mine general manager Clarence Robertson said.

“Regrettably, with the change in roster we will be reducing the number of crews at site by one and taking out some equipment, which will mean some job losses and redundancies are likely.”

While the planned number of redundancies was not revealed, Robertson said his goal was to keep as many people employed as possible.

He said Anglo had faced more than six months of delays as a result of the prolonged approval process and called the Planning Assessment Commission’s report on the project a disappointing outcome.

“We have lodged our detailed response to the PAC’s conclusions with the Department of Planning and we continue our efforts to secure the necessary project approval without further delay,” Robertson said.

“For now, the next steps for us will be determining the detail for the roster changes we need to implement and starting formal consultation with the relevant people.

“We understand this is a difficult time and we are providing our employees with assistance and support.

“We will keep everyone updated every step of the way and in the meantime, our focus will be on maintaining safety at the Drayton operation.”

Drayton has a workforce of about 500 people.

The extension project aimed to boost the mine life by 27 years and was targeting 7 million tonnes run of mine through open cut and highwall mining.

TOPICS:

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

Expert-led Insights reports built on robust data, rigorous analysis and expert commentary covering mining Exploration, Future Fleets, Automation and Digitalisation, and ESG.

editions

ESG Index 2025: Benchmarking the Future of Sustainable Mining

The ESG Index provides an in-depth evaluation of the ESG performance of 60+ of the world’s largest mining companies. It assesses companies across 10 weighted indicators within 6 essential ESG pillars.

editions

Automation and Digitalisation Insights 2025

Discover how mining companies and investors are adopting, deploying and evaluating new technologies.

editions

Mining IQ Exploration Insights 2025

Gain exclusive insights into the world of exploration in a comprehensive review of the top trending technologies, intercepts, discoveries and more.

editions

Future Fleets Insights 2025

Mining IQ Future Fleets Insights 2025 looks at how companies are using alternative energy sources to cut greenhouse gas emmissions